The contractor's schedule for the remaining work is as follows:

5/6 (on or about) to 5/14/21: Milling and paving work from 31st Street (including 31st Street) to 8th Street. During working hours, Bay Avenue will be open to two lanes of traffic, except that the rolling areas of work will be closed to traffic with traffic diverted via local detours. During non-working hours, Bay Avenue will be open to two lanes of traffic.

5/17 to 5/21/21: Pavement striping and markings will be applied over the new pavement. During working hours, Bay Avenue will be open to two lanes of traffic, except that the rolling areas of work will be closed to traffic with traffic diverted via local detours. During non-working hours, Bay Avenue will be open to two lanes of traffic.

5/24 to 5/28/21: Isolated concrete repairs, installation of vent posts and remaining punch list work. During working hours, Bay Avenue will be open to two lanes of traffic. Traffic control will consist of lane shifts around areas of work.


Ocean City, New Jersey
861 Asbury Avenue
Ocean City, NJ 08226
(609) 399-6111
www.ocnj.us 



Manage Newsletter Preferences