Final paving for this Cape May County project is set for early May. Tentative schedule is:
- April 26-30: Installation of chamber castings and lids. Isolated concrete repairs. Notification of residents of impending paving work via door hangers and car windshield tickets.
- May 3-14: Paving work from 31st Street (including 31st Street) to 8th Street.
- May 17-21: Pavement striping over new pavement.
- May 24-28: Installation of vent posts and completion of remaining punch list work.