The contractor is currently engaged in the process of installing air release valves, clean-out connections, and vent pipes within the concrete chambers that are spaced along the entire project length from 31st Street to 8th Street. As of today, the contractor has completed the chambers from 31st Street up to 24th Street, working from south to north.