The Cape May County Municipal Utilities Authority (CMCMUA) is replacing/rehabilitating the force mains that carry wastewater to the treatment plant on the bay at 45th Street. The work will be on 31st Street from Haven Avenue to Bay Avenue; and Bay Avenue from 31st Street to Eighth Street.

Work for Jan. 27-31:
 

As of the end of the day Friday (1/24/20), the contractor's south crew, which is progressing in a northward direction, will have installed PVC pipe, backfilled, and temporary paved to the intersection of 21st Street and Bay Avenue. The contractor's north crew, which is progressing in a southward direction, will have completed the same work to a point about 400 feet south of 20th Street.

Traffic:

For the weekend (1/26/20 – 1/27/20), Bay Avenue will be open to two lanes of traffic with lane shifts around stored materials and equipment. On Monday (1/20/20), Bay will be closed from 24th to 14th streets.  

Middle School Activity:

The contractor's north crew has now passed the school's busport entrance. Starting on Monday, 1/27/20, the contractor will set up a barricade at a location immediately south of the busport entrance. This will allow school buses to approach the school by driving south on Bay Avenue, and then turn left to enter the busport without conflicting with construction work. Upon exiting the busport, buses would turn right onto Bay Avenue and proceed North on Bay Avenue. A police presence will be maintained at both the intersections of 20th and Bay and 18th and Bay to supplement the efforts of the school crossing guards. The drop off of students from cars along Haven Avenue will remain unchanged.

See full project update.


Ocean City, New Jersey
861 Asbury Avenue
Ocean City, NJ 08226
(609) 399-6111
www.ocnj.us 



Manage Newsletter Preferences