North End Neighborhood Drainage Project
 

WORK TO BE COMPLETED IN THE WEEK OF MARCH 4 to 8

  • Feriozzi Concrete will restore curb and gutter in the 100 block of West Avenue. They will also restore the concrete around the pump station in the 200 block of Bay Avenue. 
  • Lafayette will work on the pump station in the 200 block of Bay Avenue. They will also begin the check valve chamber at Third Street and Bay Avenue. 
  • Delta Line Construction will continue installing the electrical from the service poles to the pump stations at all pump station locations. 