Updated 9:30 a.m. Feb. 11, 2019
North End Neighborhood Drainage Project
WORK TO BE COMPLETED IN THE WEEK OF FEB. 11 to 15
- Feriozzi Concrete will continue work on the west side of Bay Avenue, working between Fourth Street and Sixth Street.
- Lafayette will be working on the pump station in the 200 block of Bay Avenue as well as the pump station in the 500 block of Bay Avenue.
Project Design