Updated 9 a.m. Jan. 28, 2019
North End Neighborhood Drainage Project
WORK TO BE COMPLETED IN THE WEEK OF JAN. 28 to FEB. 1
- Feriozzi Concrete will continue work on the west side of Bay Avenue between Third Street and Fifth Street. They also will be doing restoration on Fourth Street between Bay Avenue and the bulkhead.
- Pipe crews will continue installing 18" force main down Sixth Street from Bay Avenue to the bulkhead.
Project Design