Email Updates

Updated 9:20 a.m. Dec. 17, 2018

North End Neighborhood Drainage Project

WORK TO BE COMPLETED IN THE WEEK OF DEC. 17 TO 21

  • Feriozzi Concrete will continue work on Pleasure Avenue between Sixth Street and Seventh Street, as well as Sixth Street from Bay Avenue to the bulkhead. 
  • Pipe crews will install inlets on Pleasure Avenue before finishing tie-ins at both Third Street and Bay Avenue and at Sixth Street and Bay Avenue. A second crew will begin installation of the pump station at Sixth and Bay. 
  • South State will begin early next week. They will be topping Third street, milling and paving Seventh Street from West to Bay, as well as Moore and Haven between 7th and 8th.
  • Arthur Henry will continue the installation of the bulkhead at Third Street. 

Project Design


Ocean City, New Jersey
861 Asbury Avenue
Ocean City, NJ 08226
(609) 399-6111
www.ocnj.us 



Manage Newsletter Preferences