Updated 12:05 p.m. Nov. 8, 2018
North End Neighborhood Drainage Project
WORK TO BE COMPLETED IN THE WEEK OF NOV. 12 to 16
- Feriozzi Concrete will finish work on Seventh Street between West Avenue and Bay Avenue, restoring curb, gutter and sidewalks. They then will begin restoration on Haven Avenue between Seventh Street and Eighth Street.
- Pipe crews will continue work between First Street and Second Street on West Avenue installing main. At the same time, a second crew will install main on Bay Avenue between Second Street and Third Street.
- Sodding will continue on Fourth and Fifth Street.
Project Design
|